Saturday 20 February 2016

Pre slab inspection

So after being stuffed around with no communication that our slab wasn't ready for pre slab inspection finally on Friday we got the green light! 
We had our independent building inspector and there was only 4 minor issues that were fixed then and there with the concrete guys. 1 of the steel wasn't tied down right and 3 were missing. All has been fixed and thank god that there were no other issues! 
Our slab gets poured on Monday the 22nd of February on a beautiful 30 degree sunny day! 
Here are some updated photos